Update on overnight resurfacing works at Derriford Roundabout


Overnight resurfacing works at Derriford Roundabout are now expected to finish overnight on Tuesday 6 February, due to poor weather earlier this week.

The revised programme means some changes to the planned closures, which are now as follows:

Friday 2 February
Lane closures only (access open on all routes)

Monday 5 February
Phase one: West section of roundabout closed, with no access from Looseleigh Lane and no access onto Tavistock Road (outbound). Traffic diverted via Looseleigh Lane, Tamerton Foliot Road and Southway Drive.
Phase two: Roundabout access to Looseleigh Lane closed. Access via Tavistock Road and Southway Drive and Tamerton Foliot Road.

Tuesday 6 February
West section of roundabout closed, with no access to or from Looseleigh Lane and no access onto Tavistock Road (outbound). Access will be via Derriford Road, Plymbridge Lane, Runway Road, Tavistock Road and Southway Drive and Tamerton Foliot Road. Traffic to exit Looseleigh Lane at Tamerton Foliot Road end.

All closures and diversions have been programmed after 7.30pm and before 6am to minimise disruption to traffic. For the latest updates follow @plymhighways and @plymouthcc on Twitter.